Surrey Hill Road

Red Jacket Engineering was engaged by New Plymouth District Council (NPDC) to address an underslip on a semi-rural road. Our team conducted a comprehensive assessment, developed multiple solution options, and provided detailed design and construction monitoring services.

After evaluating several approaches including steel pole retaining walls, gravity retaining structures, and road realignments, we determined that earth filling represented the most cost-effective solution due to the convenient availability of suitable fill material nearby. This approach optimised both project resources and long-term stability for the roadway.

This project encompassed all three teams at Red Jacket:
 
  • The Geotechnical team provided a detailed assessment of the geology
  • The Structural team developed concept designs for the retaining wall options
  • The Civil team completed the road, pavement and stormwater designs.

Scope of Services: